Limondale BESS
Lumea facilitated the connection assets provided to the Limondale Battery Energy Storage System (BESS). |
|
CLIENT | LOCATION | SERVICE | PROJECT STATUS |
RWE | Balranald Shire, NSW | Storage | Present project |
About
Lumea designed, built, and owns the designated assets required for getting power to and from the grid.
The Designated Network Assets (DNA) comprise:
220/33 kV Limondale Substation, including:
One combined 220 kV line and transformer switchbay
One 220/33 kV 250 MVA transformer
One 33/0.415 kV Auxiliary/Earthing Transformer
One 33 kV BESS connection switchbay
One 33 kV Harmonic Filter connection switchbay
Secondary services building (SSB)
Underground cabling:
Approx. 1.1 km of 220 kV single circuit underground cable connecting Limondale substation to Balranald Substation
Duplicated 72F single mode underground fibre cable between Balranald substation and the Limondale substation.